How Long Does A Bathroom Remodel Take?
It can be frustrating to estimate how long does a bathroom remodel take. Once

you believe you have the schedule in place, everything might change. Worker illness, late delivery of materials, non-payment, or unforeseen structural problems can all occur.
Accurate estimates are crucial because most homeowners must have their bathrooms operational immediately. You were having your single bathroom unavailable while remodeling is a significant annoyance unless you're fortunate enough to have others.
Phases of a bathroom full remodel and their time estimates
Three sections can be used to summarize a typical bathroom remodel timeline. We'll run you through the essential elements of a makeover below:
Divided into three phases - Pre-construction, construction, and post-construction are the three phases of a bathroom redesign.
The project is divided into these three easily manageable bathroom renovation steps.
Pre-construction
This stage involves all aspects of the organization, including the gathering of supplies, the hiring of contractors, and the preparation of written plans. This phase typically completes when all necessary permissions have been obtained.
During construction
This phase covers the bulk of the project where construction takes place. This phase entails demolishing the old area, constructing the new one, evaluating your work, and finishing the toilet.
Post-construction
After the building is complete, this phase includes a tour, detailed analyses of what was taken out and added, and contractor reflections. The job is finished, and the last payment has been made.
Pre-construction – Phase 1
We can start the bathroom remodeling the St. Louis toilet while keeping your objective in mind. Nevertheless, before moving forward, we must finish the following tasks:
Post a job.
By posting your job, you may let other professionals and contractors know your project needs. This will bring specialists with various levels of knowledge to your door, allowing you to choose whom you wish to work with. The sooner you can do this, the more options you have before a contractor's schedule fills up and your selections become more constrained.
Plan site visits and offers
It would help if you planned site visits and bids while you searched for the best contractors. Be sure the area you are creating has enough room for what you have in mind. In general, you should delay or postpone your project before moving forward if your site is not secured.
Selecting a contractor
It would help to choose your contractor once your location has been secured. Choose a contractor who can deliver because they will collaborate closely with you for weeks. Ensure their talents and work ethic are respected by reviewing their credentials. If not, you can later run into a lot of problems.
Sign the agreement and get the permits.
Once you've got a contractor, they ought to assist you in getting the required permits so you may move forward. Before proceeding with any construction project, you must obtain these permits from the city, which is informed of your intentions. Construction work cannot be done without the required permits.
You must be patient because the typical approval process can take anywhere between 6 and 8 weeks.
Be sure you'll buy all the supplies.
You can start buying supplies while you wait for the required permits to be authorized. If you have some time to wait for the permit approval and want all the materials on hand before you start the project, it is advisable to accomplish this now, before the project starts. This covers construction elements like wood and nails and upgrades like bathtubs and sinks.
Be sure you'll buy all the supplies.
You can start buying supplies while you wait for the required permits to be authorized. If you have some time to wait for the permit approval and want all the materials on hand before you start the project, it is advisable to accomplish this now, before the project starts. This covers construction elements like wood and nails and upgrades like bathtubs and sinks.
During Construction – Phase 2
Now that your necessary permits have been approved and your materials have been obtained, we can begin our project and make it easier to figure out how long does a bathroom remodel take.
Removing the old bathroom's contents
It must be removed before the building can begin on the new toilet. This entails removing all the supporting elements, including the frame and any existing fixtures, including your bathtub and washbasin. Cleaning the exposed surfaces once the old bathroom's components have been completely removed will make installing new flooring and structure easier.
Flooring, plumbing, and electrical work
Once the bathroom has been cleaned out, you may start installing the bathroom's structure and flooring. Time to remodel the bathroom, this process also entails setting up the electrical wires running through your bathroom and organizing your plumbing. Remember that this stage is just to lay the groundwork for your bathroom; no finishing touches are intended. The anticipated time windows are as follows:
Demolition time: 1-2 days
This figure will change based on how much demolition is being done. Cosmetic demolition should require a few hours to remove components like an outdated toilet or vanity. The demolition, including tearing down walls and bathtubs, will take around a day to two days to accomplish.
Plumbing and Electrical Work: Two to four days
Between contractors and the availability of professionals, this number will vary greatly. It will take 2-4 days to move the plumbing for the fixtures and alter the electrical layout. Normally, you must get this inspected before moving further with a complete remodel of the bathroom.
Drywall, painting, and insulation: one to four days
Insulation must be installed before hanging the new plasterboard. After that, fresh plasterboard can be hung, and a joint compound is applied. A day should be enough time to complete painting your plasterboard after this process, which could take up to two days.
Installation and preparation of tiles: seven days or longer
Installing tiles can be very laborious and time-consuming. This project should take a professional around a week to complete, depending on the size of your toilet. It could take between 7 and 10 days to finish if your tiler lacks skill. The project will be finished more quickly the smaller it is.
Installation of flooring: one to two days
Installing your bathroom floor should take 1-2 days, depending on size. At this period, we'll ensure the floor bonding agent dries entirely and is strong enough to sustain weight.
Conclusion
Under ideal conditions, a small complete bathroom redesign may often be completed in 23 days. If the job is done continuously without any breaks, this corresponds to around 4 1/2 weeks—just over one month—assuming no work is done on the weekends. That may be double that in the real world when downtime or unforeseen events always happen—46 days or around 9 weeks.